Milestones
- MS1 | Status: reached
Milestone name: Choice of CHON system
Related WP: WP1
Lead beneficiary: UHEI
Due date: M24
Means of verification: Deliverable 1.1- MS2 | Status: reached
Milestone name: Flowsheet for reference AMSEL system
Related WP: WP2
Lead beneficiary: FZJ
Due date: M24
Means of verification: Deliverable 2.1- MS3 | Status: reached
Milestone name: Transfer of experimental data from WP4 to WP5
Related WP: WP5
Lead beneficiary: POLIMI
Due date: M18
Means of verification: MARINE PIE, swelling measurements performed- MS4 | Status: reached
Milestone name: Completed upgrade of fuel performance codes
Related WP: WP5, WP6
Lead beneficiary: POLIMI
Due date: M36
Means of verification: Availability of upgraded versions- MS5 | Status: reached
Milestone name: Accidental scenario representative of Am-bearing fuels in off-normal situation
Related WP: WP6
Lead beneficiary: CEA
Due date: M18
Means of verification: Scenario selected- MS6 | Status: reached
Milestone name: Experimental needs for future code validation
Related WP: WP6
Lead beneficiary: CEA
Due date: M36
Means of verification: R&D needs assessed- MS7 | Status: reached
Milestone name: 7- pin fuel assembly construction
Related WP: WP7
Lead beneficiary: SCK CEN
Due date: M18
Means of verification: Technical presentation- MS8
Milestone name: Corrosion and plugging risk test performed in long term nominal conditions
Related WP: WP7
Lead beneficiary: SCK CEN
Due date: M30
Means of verification: Technical presentation- MS9
Milestone name: Post-test surface analysis performed
Related WP: WP7
Lead beneficiary: SCK CEN
Due date: M36
Means of verification: Technical presentation- MS10 | Status: reached
Milestone name: Experimental matrix defined
Related WP: WP7
Lead beneficiary: SCK CEN
Due date: M06
Means of verification: Technical presentation- MS11
Milestone name: Ageing of cladding done
Related WP: WP7
Lead beneficiary: SCK CEN
Due date: M18
Means of verification: Technical presentation- MS12
Milestone name: All material distributed to the labs
Related WP: WP7
Lead beneficiary: SCK CEN
Due date: M20
Means of verification: Technical presentation- MS13 | Status: reached
Milestone name: Profilometry and eddy current results
Related WP: WP8
Lead beneficiary: RATEN
Due date: M18
Means of verification: Technical presentation- MS14
Milestone name: Destructive analysis results
Related WP: WP8
Lead beneficiary: RATEN
Due date: M24
Means of verification: Technical presentation- MS15 | Status: reached
Milestone name: ANSYS and TRANSURANUS modelling results
Related WP: WP8
Lead beneficiary: RATEN
Due date: M36
Means of verification: Technical presentation- MS16
Milestone name: Detailed design of deformed bundle test section
Related WP: WP8
Lead beneficiary: KIT
Due date: M48
Means of verification: Technical presentation- MS17
Milestone name: Preliminary experimental results on deformed fuel assembly – first geometry
Related WP: WP9
Lead beneficiary: KIT
Due date: M54
Means of verification: Technical presentation- MS18 | Status: reached
Milestone name: Pre-test simulation of the deformed fuel assembly experiments
Related WP: WP9
Lead beneficiary: NRG
Due date: M48
Means of verification: Technical presentation- MS19 | Status: reached
Milestone name: Detailed design of porous blockage experiment in LBE [KIT]
Related WP: WP9
Lead beneficiary: KIT
Due date: M12
Means of verification: Technical presentation- MS20 | Status: reached
Milestone name: Pre-test simulations of porous blockage experiments
Related WP: WP9
Lead beneficiary: NRG
Due date: M18
Means of verification: Technical presentation- MS21 | Status: reached
Milestone name: Experimental setup of MIR tests with porous blockage
Related WP: WP9
Lead beneficiary: SCK CEN (International Partner TAMUS)
Due date: M24
Means of verification: Technical presentation- MS22 | Status: reached
Milestone name: Definition of the test matrix (based on pre-test simulations) and CIRCE experimental set-up available [ENEA, UNIPI]
Related WP: WP11
Lead beneficiary: ENEA
Due date: M48
Means of verification: Facility- MS23 | Status: reached
Milestone name: Definition of the test matrix and E‑SCAPE experimental set-up available [SCK CEN]
Related WP: WP11
Lead beneficiary: SCK CEN
Due date: M16
Means of verification: Progress Meeting Presentation- MS24 | Status: reached
Milestone name: Decision on preferred option for the modelling approach (full CFD vs. multi-scale)
Related WP: WP11
Lead beneficiary: NRG
Due date: M03
Means of verification: Progress Meeting Presentation- MS25
Milestone name: Decision on one test case for comparison among the partners [IVKDF, SCK CEN, NRG] and all models, including an attempt to use the automized heat transfer model
Related WP: WP11
Lead beneficiary: NRG
Due date: M39
Means of verification: Progress Meeting Presentation- MS26
Milestone name: Wall functions implemented for the AHFM
Related WP: WP11
Lead beneficiary: IVKDF
Due date: M18
Means of verification: Progress Meeting Presentation- MS27 | Status: reached
Milestone name: Route for automization of the AHFM selected
Related WP: WP11
Lead beneficiary: NRG
Due date: M06
Means of verification: Progress Meeting Presentation- MS28 | Status: reached
Milestone name: Coupled thermal hydraulic-chemistry codes developed
Related WP: WP12
Lead beneficiary: SCK CEN
Due date: M12
Means of verification: Technical note- MS29 | Status: reached
Milestone name: Blind benchmark on the MEXICO loop simulations performed
Related WP: WP12
Lead beneficiary: SCK CEN
Due date: M24
Means of verification: Technical note- MS30 - REMOVED
Milestone name: Improved meso-scale corrosion model of fuel assembly developed
Related WP: WP12
Lead beneficiary: KAIST
Due date: M42
Means of verification: Technical note- MS31 | Status: reached
Milestone name: Report whether attempts to prepare Os, Re, Ru doped LBE were successful
Related WP: WP12
Lead beneficiary: PSI
Due date: M48
Means of verification: Technical note- MS32
Milestone name: Models validated against experiments
Related WP: WP12
Lead beneficiary: SCK CEN
Due date: M30
Means of verification: Technical note- MS33 | Status: reached
Milestone name: Matrix isolation for the characterization of volatile tellurium molecules feasible
Related WP: WP12
Lead beneficiary: JRC
Due date: M48
Means of verification: Technical note- MS34 | Status: reached
Milestone name: Release experiments with MEGAPIE sample
Related WP: WP12
Lead beneficiary: PSI
Due date: M48
Means of verification: Technical note- MS35 | Status: reached
Milestone name: Evaluation of Tl release
Related WP: WP12
Lead beneficiary: PSI
Due date: M48
Means of verification: Technical note